Plan Analysis: Risks and Dependencies In my posting Know what you're doing (Part III) I introduced the concept of engineering plans. One of the key steps in engineering, plans or products, is analysis. Back in college, I took many analysis courses related to my major. Circuit Analysis I and II, Engineering Analysis, Statistical Analysis, and the content of many other courses stressed analysis. A good engineering education must include a good foundation in analysis. Engineering a plan is no different. I wanted to present a few analytical techniques for planning. The first in the series is risk and dependency analysis... Risk AnalysisThree common sections in a project plan are: Assumptions, Risks, and Dependencies. I hate assumptions; all assumptions are risks, you're just not planning on dealing with them. If it were up to me, the word "assume" would be banned from project plans. Dependencies are similar. If a dependency has already been satisfied, then it simply "is". If a dependency has not already been satisfied, then there's a risk that it won't be satisfied. You don't manage dependencies; you manage the risk that dependencies will not be met in a timely fashion.One way I like to analyze risks and dependencies is a simple table, with columns for:
Below is an example of a portion of a risk analysis table.
To create the above table, I have a simple CGI script (written in PERL) which allows me to edit the various fields using my web browser, and allows others (managers, my team members, and other teams) to view my risks whenever they want. I've used this successfully on several projects. [Maybe some day when I write my book, I'll include a CD with all the CGI scripts I use to lead projects. :-) ] Colors? Where did the colors come from? I've found that colorizing risks has two benefits: (1) It draws your eye to the things you should worry about the most, and (2) Managers often lack the time or attention span (and sometimes the ability) to read long sentences, so they either need cute graphics or colors. And since I'm not good enough at CGI to produce tachometer gages, traffic light graphics, or pie charts, I just colorize the rows. For my own purposes, I assume a likelihood or impact of "high" is worth 3 points, "medium" is 2 and "low" is 1. Multiplying the two together yields the overall risk: 9 is critical (red), 2 or less is under control (green) and everything in between is a serious risk (yellow). There's a fourth color: blue. I'll set the likelihood to "done" to show that the dependency has been met, or the impact to "none" if the risk has passed. "Done" and "none" have a rating of 0, so if either is 0, the risk becomes 0, so the item is closed and the row is colored blue. I might mark a risk closed and leave it in the table for a few weeks before finally deleting it. Early in the planning phase, you may come across a lot of risks, such as the risk that development will take longer, or emergent tasks will arise. But as you do analysis, you should start planning for problems and a reasonable number of emergent tasks. Once you plan for problems, then it's not a risk that those problems will arise; it's the plan. In effect, the impact drops to "none" since the plan already accomodates these problems. When you're done with the planning phase, there should (hopefully) be few true risks that your plan does not already fully address. When a good process becomes a bad methodology I found this approach to be very useful, as did others. One day someone decided to establish a formal process for creating and using the risk analysis table. Instead of CGI and a web page, they created a spreadsheet. In addition to likelihood and impact, they added "visibility" (your ability to observer the state of the risk; presumable risks that are hard to monitor warrant closer scrutiny). With three factors, all rating between 0 and 5, there were now 125 different "states" a risk could be in, so an appropriate number of colors were added to the rows -- chartreuse, fuchsia, and a few colors I didn't even know existed (and I'm not even sure they had names). The spreadsheet also included columns for things like who owned the external dependency, what was their promised date, whether they had agreed to your need date, when you talked to them last, and when the row had been last updated (just to make sure you were checking and updating your risks regularly). The spreadsheet ended up with so many columns, it was impossible to view them all at the same time, even on a 21-inch monitor. Since this was a spreadsheet and not a web page, it became more difficult to share it. I was told: post the spreadsheet on a web page, and people can download it as a file and open it. (I've found that most want information immediately, and if they have to download a file, their patience is exhausted and they don't bother.) Soon, a team of people was responsible for making sure that every project leader had a risk and dependency spreadsheet. The "Spreadsheet Police" would check periodically to make sure you were updating your spreadsheet regularly. At quarterly program reviews with the engineering vice president, we were required to display and the spreadsheet (shrunk down to an unreadable 6 point font and projected onto a screen) and discuss it with the VP. A simple, informal process had become worse than a formal process; it had become a methodology. A bad methodology. Project leaders hated the process. It didn't help them manage risks and dependencies, and only wasted their time updating useless information. Managers and VPs were frustrated because the display was too small to read and the content too detailed to absorb at their level of interest. Eventually, the entire process was scrapped. The next day, I spun up my CGI script, and I was back to using my old web page for tracking risks and dependencies, and I've been using it ever since. The moral of the story is simple: Follow the processes that help you, in a way that helps you the most. And if you do find a process that works well for you, don't tell anyone, or they'll turn it into a methodology! Posted at 09:00AM Apr 20, 2007 by Robert Hueston in Sun | Comments[2] |
|
||||||||||||||||||||||||
Robert - what a great blog... I was getting all confused over the assumptions, dependencies and risks section of my project proposal. Now I'm clear... The project does not manage assumptions or dependencies, it manages the risk of them not occuring. great stuff.
Posted by p manville on October 18, 2007 at 10:20 AM EDT #
Good to read 'real' advice that confirmed my own beleif that the whole 'RAID' Analysis was an over complicated process, created purely to make a powerful sounding acronym that consultants could boast about. After all, assumptions and dependencies are surely risks, and issues are the result of risks that materialise or unforeseen events that impact a project.
Thank you for your refreshing common sense approach and taking the time to publish it.
Posted by David Hockley on June 22, 2009 at 04:43 AM EDT #